Short answer

Flat roof installation on an Ontario commercial building follows the same order for every system: check the deck, seal a vapour retarder over it, fasten or glue insulation sloped to the drains, add a cover board, then install the membrane and flashings, sealing off each day's work. The deck, membrane and weather decide how each layer is held down.

What are the steps of flat roof installation?

Flat roof installation takes eight steps, in the same order on every commercial roof: plan the roof and apply for the warranty, check the deck, lay the deck board and vapour retarder, attach the insulation and build in the slope, add a cover board, install the membrane, finish the flashings and edges, then inspect and hand over. Only the attachment and the seams change from one system to the next.

The order of work for a commercial flat roof, common to modified bitumen, TPO, PVC and EPDM. Sources: CRCA Canadian Roofing Reference Manual, Chapter 3 (2020); IKO Technical Specification Manual, Part 4 (2025) and warranty documents (Canada); the manufacturer documents cited in our system guides. The designer and the manufacturer set the details for each roof. As of November 2026.
StepWhat happensMore detail
1. Plan and applyThe designer sets the assembly, slope and wind attachment; the roofer sends in the warranty application, at least 2 weeks ahead for IKO's Diamond ShieldPermits, warranties
2. Check the deckDry, clean and anchored, with curbs, nailers and penetrations already in placeThe deck
3. Deck board and vapour retarderOn steel, a fastened gypsum or cement board where specified; then a continuous vapour retarder, covered the same dayVapour retarders
4. Insulation and slopeUsually two layers with joints offset at least 150 mm; tapered boards where the deck is level; a sump at each drainSlope
5. Cover boardA hard board over the insulation, its joints offset at least 150 mm from those belowRoof layers
6. MembraneTorched, glued, mopped, fastened or welded, depending on the systemBy membrane
7. Flashings, edges and drainsThe membrane carried up walls and curbs, drains and pipes sealed, edge metal installedFlashings
8. Inspect and hand overSeam checks, the manufacturer's inspection and the closeout documentsChecks

Two rules run through all eight steps. Every layer goes on a dry, clean surface: CRCA's manual says insulation "must be applied under dry conditions to a clean, smooth, dry surface". And every evening the day's work is sealed off, which we cover below.

How does the roof deck change the installation?

The deck decides what can be screwed, glued or torched, so each kind is prepared differently. CRCA lists wood, structural concrete and steel as the most common roof decks in Canada, and the usual one under a commercial low-slope roof is 22-gauge steel with 38 mm ribs.

How common roof decks are prepared for a new flat roof. Sources: CRCA Canadian Roofing Reference Manual, 3.1.1 to 3.1.3 (2020); IKO Technical Specification Manual, Part 4 (2025) and InnoviTPO warranty application (Canada, 2022); NRCA, Professional Roofing (September 2017, U.S.). As of November 2026.
DeckBefore roofingHow the layers are attachedWatch for
SteelAnchored and clean, every flute dry and free of ice; where specified, a fastened gypsum or cement board at least 12.7 mm thick as a level surface and thermal barrierFasteners into the top flange only; adhesives over a deck boardWithout a board, the insulation must be stiff enough to span the ribs; closure strips in the flutes at edges and openings stop air leaks
ConcreteSmooth, trowelled and dry; primed before heat-applied layersVapour retarder, insulation and membrane can be glued straight to itNew concrete releases water for months; NRCA (U.S.) now relies on humidity probes drilled into the slab (ASTM F2170), not the old plastic-sheet test
WoodPlywood at least 15.9 mm thick for most low-slope roofs; gaps and knotholes over 6 mm covered with sheet metalIKO recommends fastening the first layer, so it can come off later without the deckNo open flame on a combustible deck
An existing roof (recover)Checked for wet insulation; IKO recommends a thermal scanFor its TPO warranty, IKO does not allow new materials to be glued to the old roof, and asks for at least 25 mm of new insulation or a cover board over itSee our recover guide

Whatever the deck, CRCA's rule is to inspect it before any material is loaded and not to start until every deficiency is corrected, because once work begins the roofer has accepted the deck. The structure itself stays with the designer; our new construction guide explains who is responsible for what.

Does a flat roof need a vapour retarder and an air barrier?

Almost always, in Ontario. The Building Code requires a vapour barrier and an air barrier system unless it can be shown they are not needed, and its own notes say few heated buildings here qualify. On a conventional roof, CRCA places the vapour retarder on top of the deck and under the insulation, on the warm side.

The two do different jobs: a vapour retarder slows moisture moving through the materials, while an air barrier stops moist indoor air leaking into the roof, which NRC named the prime cause of most condensation problems in walls and roof spaces as early as 1976. One membrane often does both, if every lap, edge and opening is sealed.

  • Continuity is the rule. The Code requires the air barrier to be continuous across junctions and around penetrations, and its notes blame most failures on poor connections. CRCA has the vapour retarder sealed to walls, curbs and drains, and carried at least 150 mm up walls above the insulation.
  • Humid buildings need more. CRCA calls for a higher grade of vapour retarder over pools, arenas and paper mills.
  • It helps hold the roof down. In NRC wind tests, mechanically attached roofs with an air barrier leaked less air and resisted uplift better than those without one.

On steel decks, CRCA and FM recommend a split system: a thin board fastened to the deck, the vapour retarder on top of it and the rest of the roof glued down, so no fastener punches through the retarder. Self-adhered retarders such as SOPREMA's SOPRAVAP'R (to -10°C) and IKO's MVP (to -5°C) go on in cold weather, but neither maker sells them as a temporary roof.

How is slope built into a flat roof?

Either the structure slopes, or tapered insulation builds the slope on a level deck. CRCA asks for every roof deck to be designed to drain at no less than 1:50 (2 per cent), and the Building Code's table for smaller buildings sets 1 in 50 as the minimum slope for modified bitumen membranes.

  • Tapered insulation is designed by the manufacturer for that roof, cut to the slope and labelled; CRCA compares installing it to a puzzle with numbered pieces and a map.
  • A sump at every drain. The insulation is tapered down at least 600 mm around each drain at 1:25, "much like a funnel".
  • Larger buildings fall under Part 5 of the Code, which sets no number but requires drainage under Section 7.4; see our drainage guide.
  • The test afterwards: no ponding 48 hours after rain, CRCA's rule of thumb. See ponding water on a flat roof.

NRC's roof design digest called slope "a most desirable practical feature of roofs", because it limits how much water gets in through any break in the membrane.

How are the layers held down: fastened, glued, torched or ballasted?

By the method of the tested assembly, because in Ontario wind resistance belongs to the whole roof. The Building Code requires the wind uplift resistance of membrane roofing assemblies to be determined under CSA A123.21, a dynamic test of complete systems held by fasteners or adhesives, unless the assembly has proven past performance for the expected wind loads.

How the layers of a commercial flat roof are held down. Sources: 2024 Building Code Compendium, Note A-5.2.2.2.(4); CRCA Canadian Roofing Reference Manual, 3.1.3 and 3.1.7 (2020); SOPREMA Canada DUOTACK data sheet (February 2026); Ontario Fire Code. As of November 2026.
MethodHow it worksUsed forTrade-offs
Mechanically fastenedScrews and plates through the insulation into the deck, in the maker's pattern; single-ply sheets fastened in their lapsInsulation on steel decks; TPO, PVC and EPDM; base sheetsWorks in any weather; each screw pierces the vapour retarder and can become a cold spot
AdheredTwo-part foam, solvent, water-based or cold adhesiveInsulation, cover boards, single-ply and modified bitumen membranesNo holes and no flame; needs dry surfaces and the right temperature, and boards set into the foam at once
Hot asphaltMopped at 1 to 1.5 kg per m² (CRCA)Built-up roofs, modified bitumen, insulationLong track record; kettles and fumes on site
Torch-appliedThe back of the roll is melted as it is unrolledModified bitumenWorks in the cold; the Fire Code requires a firewatch until at least 3 hours after torching stops
BallastedSheets laid loose under stone or paversEPDM and protected membrane roofsThe structure must carry the weight; CRCA limits it to slopes of 1:6 or less; outside the CSA A123.21 test

Corners and edges need more. Wind lifts hardest at a roof's edges, so the Code gives corners and perimeters much higher suction than the middle of the roof, and NRC researchers advise more resistance there, "e.g., by increasing the fasteners per unit area"; in one NRC example the corner load was over twice the field load. A fastener that pulls out of the deck fails the roof even when the membrane is sound, NRC notes, so fasteners go into the top flange of a steel deck.

Which membrane goes on top, and how is each one installed?

The membrane is chosen for the building, then installed by its own rules; the layers under it stay much the same. Each system has its own guide:

To choose between them, see the best flat roof system for each type of building.

How is the roof kept watertight while it is being installed?

During flat roof installation, crews put down only what can be closed in the same day and seal the edge of the new roof every night. CRCA's reference manual requires night seals or temporary membranes at the end of each day, and Sika Canada's applicator handbook allows only as much new roofing as can be made weather tight each day, flashings included.

  • Night seals. The open edge is sealed to the deck or the old roof, at a high spot and never against the flow of water (Sika), and cut away before work restarts.
  • Nothing left exposed. IKO says a vapour retarder must be covered the same day, and primers and adhesives go down only where the finished roof will cover them by evening.
  • Drains kept working. Drains are protected from debris during the day and opened every evening; CRCA suggests a small sandbag, not paper stuffed into the drain.
  • Weather first. On an existing building, no roofing is removed unless the space below can be kept watertight, with the forecast checked daily (CRCA).

Under Sika's handbook, any area where water gets under the new roofing is removed and replaced at the contractor's expense, and CRCA warns that moisture taken up by an open assembly can cause blistering at the tie-in years later. Our roof replacement guide walks through a tear-off day by day.

Can a flat roof be installed in cold weather?

Yes. In winter flat roof installation, the adhesives, tapes and self-adhered sheets set the limit, not the membranes. CRCA treats 4.4°C as the general threshold for cold-weather roofing, and IKO's cold-weather rules start below 4°C. Torch-applied, fastened and welded systems keep working well below that.

Typical cold-weather limits across flat roof systems. Sources: CRCA Canadian Roofing Reference Manual; IKO Commercial Technical Specification Manual, MVP data sheet and Innovi TPO Cold Weather Guidelines (December 2025); SOPREMA Canada, Sika Canada, Carlisle (U.S.) and Elevate (U.S.) data sheets cited in our system guides. Each product has its own limit; check its data sheet. As of November 2026.
Step or productTypical limitDetails
Cold-weather roofing in generalBelow 4.4°C (CRCA); below 4°C (IKO)Slower curing, stiffer sheets, more care
Self-adhered vapour retarder-10°C (SOPREMA SOPRAVAP'R); -5°C (IKO MVP, rolls kept at room temperature)Vapour retarders
Two-part foam insulation adhesive0°C (IKO); SOPREMA keeps DUOTACK at 0°C or warmer for 12 to 24 hours before useTanks kept warm before use
Torch-applied modified bitumenNo IKO minimum; special measures below 5°CMod bit methods
Self-adhered modified bitumen5°C and rising (IKO); -10°C for a SOPREMA winter gradeMod bit methods
Water-based membrane adhesivesAbove 4°C (Sika Canada, Carlisle, Elevate)PVC in winter
Solvent membrane adhesives4°C (IKO TPO) to -6.7°C and rising (Elevate EPDM)TPO in winter
EPDM seam tapeLoses tack below 4°C (Carlisle)EPDM in winter
Hot-air and induction weldingPVC sheet to -20°C air (Sika Canada); induction welding to -18°C (IKO)Welding in winter

How is a new flat roof checked before it is handed over?

At several points, not only at the end. The deck is inspected before materials go up, the insulation before the membrane covers it, seams as they are made, and, where a manufacturer's warranty is part of the contract, the maker inspects the finished roof before issuing the warranty.

Checkpoints during a commercial flat roof installation. Sources: CRCA Canadian Roofing Reference Manual, 3.1.2 and 3.1.3 (2020); IKO Commercial Limited Warranty Programs brochure and InnoviTPO warranty application (Canada); Sika Canada Roofing Applicator Handbook; Carlisle guide specification (U.S.). Requirements vary by manufacturer and warranty. As of November 2026.
WhenWhat is checkedWho
Before the job startsThe warranty application, with roof plan, specification and details: at least 2 weeks ahead for IKO's Diamond ShieldRoofer and manufacturer
Before materials are loadedThe deck: anchored, dry, clean, curbs and penetrations in place. CRCA: do not proceed until every deficiency is correctedRoofing foreman; the designer for the structure
Before the membrane goes onThe insulation surface: broken, wet or damaged boards are replaced (Sika)Roofing crew
Throughout the workCertified applicators on the roof: at least 2 for every 8 workers on Sika PVC systemsManufacturer's technician on request
As seams are madeTest cuts and probing of welded seams (see TPO seams)Roofing crew
At completionA notice of completion, then the manufacturer's inspection that decides whether the warranty is issuedManufacturer's field representative

A manufacturer's inspection is not the owner's inspection: Carlisle says its inspection "is not intended as a final inspection for the benefit of the owner", so an owner who wants an independent check can hire a roof consultant. Our replacement guide lists the documents you should receive at the end, and our warranty guide explains the warranty types.

What changes for flat roof installation in Toronto, Mississauga and the rest of the GTA?

The roof itself does not change from one city to the next, but the working day does. Each municipality's noise by-law sets when construction equipment such as compressors, hoists and power tools may run, and most ban it on Sundays and statutory holidays.

When construction noise is allowed under GTA noise by-laws. Sources: the by-laws and official municipal pages listed under Sources. Most limits apply where the noise can be heard at a home or in a quiet zone, and most municipalities issue exemption permits. Not listed: Burlington, Markham, Aurora, Oshawa and Hamilton; check with the municipality. As of November 3, 2026.
MunicipalityMonday to FridaySaturdaySundays and holidaysBy-law
Toronto, incl. Etobicoke, North York and Scarborough7 a.m. to 7 p.m.9 a.m. to 7 p.m.Not allowedMunicipal Code Chapter 591
Mississauga7 a.m. to 7 p.m. (5 p.m. near a quiet zone)7 a.m. to 7 p.m.Not allowed0360-1979
Brampton7 a.m. to 7 p.m.9 a.m. to 7 p.m.9 a.m. to 7 p.m.Public Nuisance By-law 136-2018
Oakville7 a.m. to 7 p.m.7 a.m. to 7 p.m.Not allowed2024-079 (since April 1, 2025)
Milton7 a.m. to 9 p.m.7 a.m. to 9 p.m.7 a.m. to 9 p.m.133-2012
Halton Hills7 a.m. to 7 p.m.8 a.m. to 6 p.m.Not allowed2010-0030
Caledon6 a.m. to 11 p.m.6 a.m. to 11 p.m.8 a.m. to 8 p.m.86-110
Vaughan7 a.m. to 7 p.m.7 a.m. to 7 p.m.Not allowed121-2021
Richmond Hill7 a.m. to 7 p.m.7 a.m. to 7 p.m.Not allowed43-20
Newmarket7 a.m. to 8 p.m.9 a.m. to 5 p.m.9 a.m. to 5 p.m.2024-08
Pickering7 a.m. to 7 p.m.9 a.m. to 6 p.m.Not allowed8048/23
Ajax7 a.m. to 8 p.m.7 a.m. to 8 p.m.7 a.m. to 8 p.m.04-2026
Whitby7 a.m. to 8 p.m.7 a.m. to 8 p.m.Not allowed6917-14

Several of these by-laws changed recently: Oakville, Newmarket and Ajax have new ones since 2024, and Vaughan banned Sunday construction in 2024. Work outside these hours needs an exemption applied for well ahead: at least 28 days before the work in Toronto, 45 days in Oakville and 90 days in Vaughan. Building permits are a separate question, covered city by city in our permit guide, and the wind a roof is designed for rises toward the lakeshore, as our roof system guide explains.

Which flat roofs has OYH Roofing installed?

Our flat roof installation work so far includes seven published projects in modified bitumen, TPO and PVC, on new buildings, an addition and existing buildings.

Drone view of the finished 52,300 sq ft IKO 2-ply modified bitumen roof at 777 Niagara St in Welland, with rooftop units on curbs
The finished 52,300 sq ft IKO 2-ply modified bitumen roof at 777 Niagara St, Welland, which carries a 20-year system warranty. Each curb under a rooftop unit is a detail the membrane has to be flashed around.

See all our completed projects. We also install EPDM and built-up roofing, listed on our services page.

Frequently asked questions

What are the steps involved in installing a flat roof professionally?

A professional crew first checks and accepts the deck, then installs the layers in order: a deck board where needed, a sealed vapour retarder, insulation sloped to the drains, a cover board, the membrane, and the flashings at walls, curbs, drains and edges. Each evening the day's work is sealed off, and at the end the roof is inspected and documented before handover.

What are the downsides of a flat roof?

Water drains slowly, so a flat roof depends on slope built into the insulation, clear drains and sound flashings; water still standing 48 hours after rain shortens its life. The membrane is the only waterproofing, so a puncture can leak, and snow stays on the roof instead of sliding off. Flat roofs need inspections at least twice a year and after storms.

Do flat roofs have joists or rafters?

Joists or beams, not rafters, which belong to pitched roofs. Most commercial flat roofs in Ontario have a ribbed steel deck fastened to steel joists or beams, or a concrete slab; smaller wood-frame buildings use wood joists under plywood. The slope a flat roof needs comes from sloping the structure or from tapered insulation laid on top of it.

Do you put shingles on a flat roof?

No. Shingles shed water only on a slope: Ontario's Building Code allows asphalt shingles down to 1 in 3 normally, or 1 in 6 with a special low-slope application. A flat roof sloped at about 1 in 50 needs a continuous membrane instead, such as modified bitumen, TPO, PVC, EPDM or built-up roofing, sealed at every lap and flashing.

What is the best way to roof a flat roof?

As a complete, tested system rather than a membrane on its own. The deck, the use of the roof and the weather during installation decide which system. On most Ontario commercial roofs that means 2-ply SBS modified bitumen or a 60 mil single-ply sheet over insulation and a cover board, held down the way the system was tested for wind, with slope built in to the drains.

Planning a new flat roof?

Tell us about the building, the deck and what sits on the roof, and we will set up a roof assessment and a written quote.

Call 1-833-775-7663Request an assessment
Karol Rajkowski, Vice President of OYH Roofing

Karol Rajkowski

Vice President · OYH Roofing

Karol Rajkowski is Vice President of OYH Roofing, an Oakville-based ICI flat-roofing contractor whose projects include the 2-ply modified bitumen roof on the new Marriott Hotel in Vaughan and the 50,000 sq ft TPO roof across a new addition and the existing building at Millomat Stampings in Mississauga. Learn more about the OYH team.