In this TPO roofing Pickering project, OYH Roofing re-roofed the Devi Mandir temple in Pickering, Ontario. The crew tore off two existing layers of modified bitumen and the coating on top, then installed a 60 mil TPO system across 6,500 square feet. The roof carries a 20-year warranty on labour and materials.

Project details

This TPO roofing Pickering project covered a 6,500 square foot roof on a temple. Here is the TPO roofing Pickering job in one table.

Source: OYH Roofing project record for Devi Mandir. As of October 2026.
ItemDetail
ClientDevi Mandir
LocationPickering, Ontario
Building typeTemple (institutional)
Roof area6,500 sq ft
ServiceTear-off of two modified bitumen layers and a coating, then re-roof
System60 mil TPO single-ply membrane
Warranty20 years on labour and materials
TPO roofing Pickering project at the Devi Mandir temple
The TPO roofing Pickering project at Devi Mandir.

When does a coated, layered roof need a full tear-off?

A coated, layered roof needs a full tear-off when the membrane under the coating has reached the end of its life, because another coating or another layer only covers the problem.

The old roof on this temple had been built up over the years: two layers of modified bitumen with a coating applied on top. A coating can extend the life of a sound roof, and it costs less than a replacement, but it cannot fix a membrane that has already failed. On this TPO roofing Pickering job the old layers and the coating were removed before the new roof went on. Here are the signs we look at on TPO roofing Pickering jobs.

General guide to coating, overlay or tear-off on a low-slope roof. Every roof needs its own assessment. As of October 2026.
What the roof showsWhat it usually meansUsual direction
One sound layer, surface wear onlyThe membrane still has life in itRepair or coating
More than one existing layerExtra weight on the structure, and moisture can be trapped between layersTear-off
A coating over a failing membraneThe coating is hiding the problem, not fixing itTear-off
Soft or spongy areas underfootOften wet insulation or a damaged deckTear-off, with deck repairs as needed
Leaks that keep movingThe system as a whole is at the end of its lifeTear-off

Why 60 mil TPO for a temple roof in Pickering?

A 60 mil TPO membrane suits a community building because its seams are welded with hot air, its white surface reflects summer heat, and it needs little upkeep once it is installed.

TPO (thermoplastic polyolefin) is a single-ply membrane. Mil is the thickness, one thousandth of an inch, so a 60 mil sheet is thicker than the 45 mil sheets used on lighter-duty roofs. On a temple, a leak disrupts services and damages the interior, so durability matters. TPO is not the right answer for every building, so here is how it compares with the other systems we install.

General comparison of flat roofing systems OYH Roofing installs, for owners weighing TPO roofing Pickering options. The right system depends on the building. As of October 2026.
SystemLayersWhere it winsWhere another system wins
60 mil TPOSingle ply, hot-air welded seamsWelded seams, reflective white surface, light weightOne layer; modified bitumen is tougher under heavy foot traffic
2-ply modified bitumenBase sheet plus cap sheetToughest underfoot, two layers of protectionHeavier, and a dark surface absorbs more summer heat
Roof coatingLiquid applied over the existing roofCosts less than a replacementShorter-lived, and only works over a sound membrane

Industry guidance from the National Roofing Contractors Association points to the details on single-ply roofs: seam quality and the flashings at curbs, drains, vents and parapets decide how long the roof lasts.

60 mil TPO roof on the Devi Mandir temple in Pickering
The 60 mil TPO membrane on this TPO roofing Pickering project.

What does the 20-year labour and materials warranty cover?

This TPO roofing Pickering project carries a 20-year warranty on labour and materials, so both the membrane and the workmanship are covered.

The exact coverage, and what the owner has to do to keep it valid, is set by the written warranty terms. That usually includes regular inspections and keeping records of any work done on the roof, as on any TPO roofing Pickering project. Ask for the warranty document for your project and keep it with the building records.

How do you maintain a TPO roof on a community building?

A TPO roof needs an inspection at least twice a year, in spring and fall, plus a check after major storms. Temples, churches and community centres often have small maintenance budgets, so a short, fixed routine works best on any TPO roofing Pickering project.

Typical maintenance plan for a low-slope TPO roof, based on the NRCA recommendation of at least two inspections a year. As of October 2026.
WhenWhat to check
Spring, after the snow meltsSeams, flashings, drains, any damage from ice or ponding
Fall, before winterClear drains and scuppers, check flashings at curbs and parapets
After major stormsWind or debris damage, blocked drains
Every rooftop service visitCrews stay on walkway pads; keep oils and grease off the membrane

Staff and volunteers should not walk the roof themselves, especially in winter or wet weather. Book the inspection and let a roofing crew do it with proper fall protection. We offer inspections to every TPO roofing Pickering client.

Photos of the roof

Photos of this TPO roofing Pickering project at Devi Mandir.

TPO roofing Pickering services from OYH Roofing

OYH Roofing takes on TPO roofing Pickering projects from its Oakville head office and installs industrial, commercial and institutional flat roofs across the Greater Toronto Area and the rest of Ontario.

Our commercial roofing services cover TPO, PVC, EPDM, modified bitumen and built-up roofing, plus inspections and commercial roof leak repair. The same 60 mil TPO went on the 50,000 square foot roof at Millomat Stampings in Mississauga, and you can see the rest of our work on the completed projects page.

Planning TPO roofing work in Pickering?

For TPO roofing Pickering work, tell us about the building and we will set up a free roof assessment and a written quote.

Call 1-833-775-7663Request an assessment

Frequently asked questions

Can a coated modified bitumen roof be overlaid instead of torn off?

A coated modified bitumen roof can sometimes be overlaid, but not when there are already two layers and the membrane underneath has failed. At Devi Mandir in Pickering, both layers of modified bitumen and the coating were torn off, and a new 60 mil TPO system was installed across the 6,500 square foot roof.

How long does a 60 mil TPO roof last?

A 60 mil TPO roof commonly lasts 20 years or more when it is installed as a full system and inspected twice a year. The Devi Mandir roof carries a 20-year warranty on labour and materials, which reflects that expected service life. Blocked drains, punctures from foot traffic and skipped inspections are what usually shorten it.

Is a roof coating cheaper than a roof replacement?

A roof coating is cheaper than a roof replacement, but it is shorter-lived and it only works over a membrane that is still sound. Over a failed membrane, a coating hides the problem for a while and the leaks come back. A roof assessment by a commercial roofer shows which option fits your building.

What is the difference between 45 mil and 60 mil TPO?

The difference between 45 mil and 60 mil TPO is thickness. A mil is one thousandth of an inch, so a 60 mil membrane is one third thicker than a 45 mil membrane. The thicker sheet gives more resistance to punctures, which is why 60 mil was used on the Devi Mandir roof.

Does OYH Roofing work on temples, churches and community buildings?

OYH Roofing works on temples, churches and community buildings, and the 6,500 square foot re-roof at Devi Mandir in Pickering is one example. The company is based at 2120 Speers Rd in Oakville and installs, repairs and inspects industrial, commercial and institutional flat roofs across Ontario. Call 1-833-775-7663 to book an assessment.

Karol Rajkowski, Vice President of OYH Roofing

Karol Rajkowski

Vice President · OYH Roofing

Karol Rajkowski is Vice President of OYH Roofing, an Oakville-based ICI flat-roofing contractor whose projects include the City of Mississauga building at 3185 Mavis Rd and the Marriott Hotel in Vaughan. Learn more about the OYH team.

Sources

OYH Roofing, 2120 Speers Rd, Oakville, ON L6L 2X8 · 1-833-775-7663 · info@oyhroofing.ca