Commercial Roofing for Property Managers in Ontario
How a property manager keeps track of every roof, handles a leak without voiding the warranty, writes a roof tender, and stays on the right side of Ontario's safety, payment and tenancy rules.
Call 1-833-775-7663 Oakville head office · Flat roofing for property managers and building owners across the GTA
Karol Rajkowski
Vice President, OYH Roofing
Published November 10, 2026 · 12 min read
Short answer
Commercial roofing for property managers comes down to four jobs: keep a file and a condition rating for every roof, report leaks to the membrane maker within the warranty's deadline, buy roof work with a clear scope and tender, and manage the contract. In Ontario, a property manager counts as an "owner" under the Occupational Health and Safety Act, and one who hires several contractors at once can become the "constructor".
How should a property manager keep track of every roof?
Good roofing for property managers starts with one roof file per building and a condition rating for each roof area. BOMA BEST, the Canadian building certification many commercial landlords use, asks for a condition assessment of the building envelope within the past five years that lists "the envelope (roof, wall, skylight, etc.) components, installation date and anticipated remaining useful life", and highlights what will need replacing in the next ten years. Its mandatory preventive maintenance credit adds an inventory of systems and a plan signed and dated within the last 12 months.
Lenders and buyers look at the same papers. A guide to building condition assessments from the Agency for Co-operative Housing says an assessment "should be updated every five years", and that a lender "will prefer a report no more than three years old".
| Item | Why it matters |
|---|---|
| Roof plan with numbered roof areas, drains, hatches and rooftop units | Lets every leak report, quote and invoice point to the same place |
| Installation date, system and maker for each roof area | Sets the remaining life in the capital plan and tells you which warranty applies |
| Warranty certificates and the maker's owner's guide | The guide sets the maintenance the warranty depends on; notice deadlines are in the certificate |
| As-built drawings, specifications and the contract | Needed for the next tender and for any warranty or lien question |
| Inspection reports with photos, and the latest condition assessment | Show the roof's trend and back up insurance and warranty claims |
| Leak log and repair invoices | Repeated leaks in one area are the clearest sign a roof section is near the end |
| Rooftop access log (who went up, for what) | Ties new damage to the trade that caused it |

Our roof inspection guide covers what each inspection report should contain, and our roof maintenance guide covers the yearly program and its records.
How do you plan roof replacements across a portfolio?
Rank the roofs by condition and remaining life, then put them in a ten-year capital plan. BOMA BEST describes the split many managers use: "Tactical items are those that will require attention within the first five years", while strategic items are "typically reviewed in the 10-year capital asset management plan". A roof in the tactical window needs a budget line and a consultant now; one in the strategic window needs inspections and repairs that keep it there.
- Start from condition, not age. A 15-year-old roof with dry insulation can outlast a 10-year-old one with wet insulation. A moisture survey shows which is which; see how roof consultants score a roof's condition.
- Use realistic service lives. Our commercial flat roof lifespan guide gives published ranges by system.
- Group work by building, not by roof area. Replacing two adjacent roof sections in one contract shares the crane, the bins and the mobilization.
- Allow a year of lead time. Assessment, design, tender and approvals usually take most of the year before the work.
For one building that is near the end of its roof's life, our roof replacement guide walks through the stages of the job itself.
What should a property manager do when a roof leaks?
Protect people and contents, then report the leak to the membrane maker in the way and time the warranty requires, before anyone cuts into the roof. Warranty notice deadlines are short and they differ:
| Term | Sika Canada (Sarnafil system warranty) | IKO (Diamond Shield sample) |
|---|---|---|
| Leak notice | Notify Sika "on the first business day immediately following the discovery of each leak" and confirm in writing within one week | Written notice "within 30 days following the discovery"; late notice makes the warranty "null and void" |
| Repairs by others | Repairs or alterations on or through the roof without Sika's written authorization void the warranty | Owner must give IKO access to inspect; refusing access voids it |
| Maintenance | Reasonable care as described in the owner's guide | A maintenance program recommended by NRCA or CRCA |
| Sale of the building | Not assignable unless Sika approves in writing | Transferable once, with 30 days' notice and a $750 fee |
In practice, the first hours look like this:
- Make the area safe: power off wet fixtures, put out buckets and tarps, move stock and equipment.
- Record it: photos of the ceiling and the roof above, the date and time, the weather, and the roof area from the roof plan.
- Call the roofer who holds the workmanship warranty, or the maker's listed contractor, and send the written notice to the maker the same day.
- Let the roofer make a temporary seal only as far as the warranty allows; keep the materials and photos.
- Tell your insurer promptly if there is interior damage; see how to file a roof leak insurance claim.
Finding the source is a separate job from stopping the water; our flat roof leak detection guide explains the methods.
What do tenants and residents need to be told about roof work?
It depends on the tenancy. In a residential rental building, the Residential Tenancies Act makes the landlord keep the complex "in a good state of repair", and Ontario's maintenance standards say plainly: "Every roof shall be watertight." A landlord may enter a unit without written notice in an emergency, such as water coming through a ceiling. To come back for a repair or inspection, it must give 24 hours' written notice stating the reason, the day and a time between 8 a.m. and 8 p.m.
For a roof replacement over occupied apartments, notice protects the landlord as well. Under the Act's general regulation, the Landlord and Tenant Board cannot order a rent abatement for the work if, among other conditions, tenants got at least 60 days' notice describing the work, its expected impact and how long it will take, and the work followed the local noise by-law. Our apartment building guide covers the work with tenants at home.
In commercial buildings, the lease decides. Ontario's Commercial Tenancies Act says nothing about roof repairs, and courts read each lease's repair, replacement and capital-cost clauses closely: in 402 Mulock v. Wheelhouse (2022), the Court of Appeal treated replacing the roof membrane on a whole building as a "capital repair or replacement". See who pays for plaza roof repair for the leading cases, including the 2026 Hillmond appeal.
What goes into a roof scope of work and tender package?
Enough detail that every bidder prices the same job. The Canadian Roofing Contractors Association's manual says re-roofing specifications usually need more protection for the owner's property than new work, and sets two rules a good scope repeats: no more roofing removed in a day "than can be properly made watertight at the end of each day", and "Under no circumstances should any new roofing be installed over wet or otherwise deteriorated roof insulation."
| Part of the package | What to include |
|---|---|
| Scope and drawings | Roof areas by number, the new system, insulation, slope, flashings, drains, curbs and equipment to lift |
| Existing conditions | Moisture survey or core results, the asbestos and designated substances report, structural limits |
| Bid form | A lump sum plus unit prices for hidden work, such as deck or wet insulation replacement per square foot, used only with the owner's written approval |
| Site meeting | One mandatory walk-through so every bidder sees the roof and the access |
| Site rules | Working hours, hoisting and bin locations, interior protection, tenant notices, daily watertight tie-ins |
| Warranty | The maker's warranty term and type (for example a 15-year no-dollar-limit warranty) plus the roofer's workmanship guarantee |
| Quality checks | Maker's inspections during the work (the 2019 specification asked for visits at about 30, 60 and 90 per cent) and a final inspection |
| Contract | Usually CCDC 2, the standard stipulated price contract, with the owner's supplementary conditions |
CCDC 18 is a civil works contract for roads and bridges, not a short form for roofing. Our guide to comparing roofing quotes covers how to read the bids that come back, and the best flat roof system guide covers comparing proposals for different systems.
When does the owner or property manager become the "constructor"?
When it hires more than one contractor for the same project and nobody else takes control. Ontario's Occupational Health and Safety Act defines "owner" to include "a person who acts for or on behalf of an owner as an agent or delegate", which covers a property manager, and a "constructor" includes an owner who undertakes a project "by more than one employer". The constructor carries the project's legal safety duties.
The Ministry's constructor guideline puts it this way: an owner that contracts with more than one contractor "could become the constructor if no general contractor has been retained and the separate contractors work at the same time", and without an agreement that one contractor accepts the role, "the owner will likely be deemed the constructor". A common roof example is hiring a roofer and, separately, a mechanical contractor to disconnect and lift the rooftop units during the same week.
There are three clean ways to avoid it: put the whole job under one contract (the roofer subcontracts the mechanical and crane work), schedule the trades so they do not overlap, or agree in writing that one contractor takes control as constructor. A constructor must also file a Notice of Project with the Ministry before starting when labour and materials are expected to exceed $50,000, which covers most re-roofing jobs.
What should a property manager collect before the roofer starts?
- WSIB clearance certificate, valid for the whole job; see what WSIB clearance means.
- Insurance certificate naming the owner and the manager as additional insureds. Large landlords set their own limits; Cadillac Fairview's form for one Toronto office tower, for example, asks contractors for at least $5 million of general liability and says general contractors' policies must cover their sub-trades.
- Notice of Project copy and the constructor's name, if the job needs one.
- The schedule, the hoisting and bin plan, and the hot work and fire watch plan for torch work (see torch-on roofing over a working building).
- Safety program evidence. COR certification from the Infrastructure Health and Safety Association is voluntary in Ontario, but some owners ask for it; it lasts three years with internal audits in the second and third years.
The Canadian Roofing Contractors Association warns owners that "If a contractor is not properly insured, you, the owner may be liable for accidents that occur on the property." Our contractor checks list the rest.
How does paying a roofer work under Ontario's Construction Act?
By the Act's prompt payment rules, which apply to private owners as well as public ones:
- 28 days. The owner must pay a proper invoice within 28 days of receiving it.
- 14 days to dispute. To withhold any amount, the owner must give a notice of non-payment in the prescribed form within 14 days.
- 7 days to flag a deficient invoice. Since January 1, 2026, an invoice missing required items is treated as proper unless the owner points out the gap in writing within seven days.
- 10 per cent holdback. The owner keeps 10 per cent of each payment until the lien period has passed.
Holdback release changed on January 1, 2026. For longer contracts, the owner must now publish a notice of annual release within 14 days after each contract anniversary and pay the accrued holdback 60 to 74 days later. On a roof job finished within the year, the holdback is due 14 days after liens expire, which is normally 60 days after substantial performance is published or the contract is completed. Disputes over payment can go to adjudication; our institutional roofing guide explains it.
What is different for condominium property managers?
A condo manager needs a licence to do the roofing work of a property manager. Under the Condominium Management Services Act, negotiating or entering into contracts and supervising contractors for a condominium corporation are licensed "condominium management services". A manager with an interest in a contract must disclose it in writing, and get the corporation's written approval before signing it, even with delegated authority.
The regulations also require written disclosure of any "direct or indirect financial benefit" the manager may receive from another person, which covers referral fees from contractors, and bar gifts that a reasonable person might think could influence the manager. A manager with a limited licence cannot sign a contract or spend more than $500 of the corporation's money without the supervising licensee's approval, except to keep people safe, and cannot spend from the reserve fund. The board's own duties, votes and reserve fund rules are in our condo roof replacement guide.
How does OYH Roofing handle roofing for property managers?
OYH Roofing is an Oakville-based industrial, commercial and institutional roofing contractor offering roof replacements, new construction installations, repairs, inspections and emergency services, listed on our services page. Our published projects cover the systems most property managers own:
- Millomat Stampings, Mississauga: 60 mil TPO across a new addition and the existing building, 50,000 sq ft, 20 years on labour and materials (the photo above).
- 777 Niagara St, Welland: IKO 2-ply modified bitumen, 52,300 sq ft, 20-year system warranty.
- Residential building, Sault Ste. Marie: PVC, 17,500 sq ft, 30 years on labour and materials.
- City of Mississauga, 3185 Mavis Rd: IKO 2-ply on a municipal building, 8,500 sq ft, 20-year system warranty.
See all our completed projects.
Frequently asked questions
What should a property manager do when a roof leaks?
Make the area safe and protect contents, record the leak with photos, the time, the weather and the roof area, and call the roofer. Then send written notice to the membrane maker within the warranty's deadline: Sika Canada's sample warranty wants a call the next business day and written confirmation within a week, and IKO's sample voids the warranty if notice comes later than 30 days. Avoid repairs by others the warranty does not allow.
What to do if the roof is leaking in an apartment in Ontario?
Tell the landlord or property manager right away, in writing as well as by phone. The Residential Tenancies Act makes the landlord keep the building in good repair, and Ontario's maintenance standards require every roof to be watertight. The landlord may enter without written notice in an emergency; otherwise it must give 24 hours' written notice. A tenant whose leak is not repaired can apply to the Landlord and Tenant Board.
Who is responsible for roof repairs in a commercial lease in Ontario?
Whoever the lease says. Ontario's Commercial Tenancies Act does not divide roof costs, so it comes down to the repair, replacement and additional rent clauses. Many leases leave structural and roof replacement work with the landlord and pass routine repairs through as operating costs, but wording varies. Courts read those clauses closely: the Court of Appeal has treated a full roof membrane replacement as a capital repair or replacement, not ordinary maintenance.
Is a property manager the constructor under Ontario's OHSA?
Sometimes. A property manager acting for the owner counts as an owner under the Occupational Health and Safety Act. If it hires one roofer for the whole job, the roofer is normally the constructor. If it hires separate contractors who work at the same time, with no general contractor and no written agreement giving one of them control, the Ministry says the owner will likely be deemed the constructor.
How often should a property manager have roofs inspected?
Spring and fall visits are the usual minimum, plus checks after storms and after other trades work on the roof, with a full condition assessment about every five years. BOMA BEST asks for an envelope condition assessment within the past five years, and a building condition assessment guide notes that lenders prefer one no more than three years old. Many roof warranties also require regular maintenance, so keep the reports in the roof file.
Managing roofs across several buildings?
Send us the addresses, the roof areas and any inspection reports, warranties or tender documents you already have, and we will review the roofs and the scope with you.
Call 1-833-775-7663Request an assessment
Karol Rajkowski
Vice President · OYH Roofing
Karol Rajkowski is Vice President of OYH Roofing, an Oakville-based ICI flat-roofing contractor whose projects include the 50,000 sq ft TPO roof at Millomat Stampings in Mississauga and the 52,300 sq ft IKO 2-ply modified bitumen roof at 777 Niagara St in Welland. Learn more about the OYH team.
Sources
- Ontario laws (e-Laws): Occupational Health and Safety Act, ss. 1 and 23; O. Reg. 213/91, Construction Projects, s. 6 (consolidation from April 20, 2026); Construction Act, ss. 6.1, 6.4, 22, 26 and 31 (consolidation from January 1, 2026); Residential Tenancies Act, 2006, ss. 20, 26 and 27; O. Reg. 516/06, s. 8; O. Reg. 517/06, Maintenance Standards, ss. 6 and 7; Commercial Tenancies Act; Condominium Management Services Act, 2015, ss. 1, 34 and 52; O. Reg. 123/17, ss. 8 and 32; O. Reg. 4/18, s. 5; O. Reg. 3/18, s. 14.
- Ministry of Labour, Immigration, Training and Skills Development, Constructor guideline (updated August 13, 2026). Condominium Management Regulatory Authority of Ontario, Code of Ethics: Declaring Conflict of Interest (2024).
- Leases: Law Times, on 402 Mulock Investments Inc. v. Wheelhouse Coatings Inc., 2022 ONCA 718 (November 2, 2022); McMillan LLP, Repair and Replacement in Commercial Leases (June 2026).
- Industry: BOMA Canada, BOMA BEST 4.0 Offices Field Guide (June 2023), E1.2, E2.2 and E6.0; Agency for Co-operative Housing, Guide to Building Condition Assessments and Reserve Fund Studies (March 2018); CRCA, Canadian Roofing Reference Manual, 3.2.1 to 3.2.3, and Selecting a Roofing Contractor (April 2014); Infrastructure Health and Safety Association, COR FAQs; Cadillac Fairview, General Liability Insurance Requirements (RBC Centre, 2019).
- Specifications and warranties: Leeds, Grenville and Lanark District Health Unit, Specification for the Roof Replacement at 458 Laurier Blvd., Brockville (May 2019); Sika Canada, Sample Sarnafil System Warranty (March 2022); IKO, Diamond Shield limited warranty sample, MT1L051 (2021).
OYH Roofing, 2120 Speers Rd, Oakville, ON L6L 2X8 · 1-833-775-7663 · info@oyhroofing.ca