Short answer
Apartment building flat roof repair in Ontario is the landlord's job, and it is urgent. Ontario's maintenance standards say "Every roof shall be watertight", and in Toronto a leak counts as a building envelope breach that needs a response within 24 hours. Find where the water really comes from, dry the unit below within 24 to 48 hours to stop mould, then make a lasting repair. Tenants who wait too long can ask the Landlord and Tenant Board for rent abatements and repair orders.
Why do apartment building flat roofs leak?
At the same weak points as any flat roof, plus a few that apartment buildings add. The Canadian Roofing Contractors Association (CRCA) manual warns that "The location and cause of water leaks does not always occur directly from above", and on a steel deck the flutes "act as gutters, allowing water to travel a long distance before finding an opening". It names the usual suspects: "roof penetrations such as roof anchors, exhaust vents, drains etc."
| Where | Why it leaks | More detail |
|---|---|---|
| Plumbing vents and exhaust stacks | One for every stack of units; leaks once "the caulking around pipe penetrations begins to deteriorate" | Flashing repair |
| Roof anchors and window-cleaning davits | Many fastened points around the edge of taller buildings | Office building roofs |
| Rooftop and make-up air units | Curb flashing, condensate lines and service traffic | Rooftop equipment |
| Penthouse and parapet walls | Copings, wall flashing and masonry | Parapet repair |
| Roof drains | Blocked or frozen drains hold water against the membrane | Drainage repair |
| Satellite dishes and antennas | Fastened through the roof by tenants or providers; Ottawa Community Housing bans tenant dishes on "Any part of the roof" | Set a written rule |
Not every drip is the roof. CMHC's sample leak report form for tenants asks whether the leak is "near hydronic piping/radiators", whether it happens "every time it rains" and whether it is "near an air-conditioning unit": heating pipes, condensate lines and plumbing from the unit above can all look like a roof leak. Our leak detection guide covers how roofers trace water under a membrane.
What should a landlord do in the first 24 to 48 hours?
Respond the same day, stop the damage, and find out whether it is really the roof. CMHC's operations manual for rental buildings puts it simply: "Leaks and other moisture issues should always be dealt with immediately." A practical order of work:
- Answer the tenant and log it. Record the date, time, unit and what the tenant saw. In Toronto, Mississauga and Ottawa a response within 24 hours is the rule for urgent requests (see the city rules below).
- Protect the unit. Buckets, plastic over furniture, power off to wet light fixtures. A landlord may enter without written notice in an emergency; our property manager's guide covers the entry rules.
- Check the units below and beside. Water travels, so the unit that reported it may not be the only wet one.
- Call the roofer and the warranty holder. Many roof warranties have short notice deadlines; our property manager's guide lists two of them.
- Start drying. Wet ceiling tiles and insulation come out, and wet drywall is dried within 24 to 48 hours (see mould below).
- Document everything. Photos of the ceiling and the roof, the weather, and every visit. The construction industry's mould guideline says "All incidents of wet materials should be documented as part of due diligence."
What does Ontario law require of landlords for roof leaks?
A watertight roof, kept that way, and a landlord cannot contract out of it. The Residential Tenancies Act makes the landlord keep the building "in a good state of repair and fit for habitation" and comply with "health, safety, housing and maintenance standards" (s. 20(1)), even if the tenant knew about the problem before moving in (s. 20(2)).
Which standards apply depends on the city. Most GTA municipalities have a property standards by-law; Toronto's requires every roof to be "weather-tight and free from leaks" (Chapter 629, s. 629-20). Where no by-law applies, and inside units where a by-law covers only the outside, the province's maintenance standards fill the gap (RTA s. 224; O. Reg. 517/06, s. 4). The Landlord and Tenant Board's guideline reads s. 20 as "only those standards which are enforceable for that complex". The provincial standards are the clearest statement of what is expected:
| Section | What it says |
|---|---|
| Roofs (s. 7) | "Every roof shall be watertight." The roof and its flashing, coping, gutters, rainwater leaders and vents "shall be maintained to properly perform their intended function" and kept clear of "dangerous accumulations of snow and ice" |
| Walls and roofs (s. 6(1)) | Must be "structurally sound, weathertight and damp-proofed" and protected against deterioration, "including that due to weather, fungus, dry rot" |
| Drainage (s. 9(1)) | Plumbing and drainage systems "maintained free from leaks, defects and obstructions and adequately protected from freezing" |
| Ceilings (s. 39) | Walls and ceilings "maintained free from holes, leaks, deteriorating materials, mould, mildew and other fungi", with "A protective finish" on repairs |
| Workmanship (s. 3) | Repairs done "with the materials that are accepted as good workmanship in the trades concerned" |
Enforcement starts with a complaint. Under a city by-law, a property standards officer can order the repair; under the provincial standards, an inspector can issue a work order with a deadline (RTA s. 225), which the landlord can ask the Landlord and Tenant Board to review within 20 days (s. 226). The Board's guideline treats any such order as "a finding by a public official that the landlord has not complied with the standard". Entry to units and notice for roof work are covered in our property manager's guide.
What do Toronto's RentSafeTO and other city by-laws add?
Response deadlines, logs and a written roof plan. Toronto, Mississauga and Ottawa each have an apartment building by-law on top of property standards, and all three name roofs in the capital plan they require:
| City | Buildings covered | Response times | Roof in the capital plan |
|---|---|---|---|
| Toronto (RentSafeTO, Chapter 354) | Rental buildings with 3 or more storeys and 10 or more units | Urgent requests within 24 hours, including a "breach of ... building envelope"; others within 7 days | A "comprehensive five-year forecast" listing "(1) roofs" first among capital elements, with a replacement date |
| Mississauga (By-law 0089-2022) | 2 or more storeys and 6 or more units | Urgent within 24 hours, including an issue that can "make a Rental Unit uninhabitable"; others within 5 days | A 5-year state of good repair plan; the city's sample plan lists "Roof membrane, flashing or anchors" |
| Ottawa (By-law 2020-255) | 3 or more storeys or 10 or more units | Urgent within 24 hours, including issues that could make a unit uninhabitable; others within 7 days | A capital maintenance plan with each roof's last inspection date, condition and planned work |
Toronto's rules go furthest. Every service request must be logged with the date, time, unit and response, and records kept for at least 24 months (s. 354-4.1). The roof is a capital element that must appear on the building's notification board when a major project starts, and tenants can ask for the five-year plan, which the landlord must hand over within 60 days.
City officers evaluate each building once every 2 years, looking at the exterior "including condition of cladding/bricks/paint, flashing, and drain pipes" and at common-area ceilings, and since June 15, 2026 the score has to be posted at the entrance on a green, yellow or red sign. The by-law says "building envelope" rather than "roof", but water through a roof is a breach of the envelope, so treat a leak report as urgent: respond within 24 hours, even if the repair takes longer.
What can tenants claim at the Landlord and Tenant Board?
If a leak is not fixed, a tenant can file a T6 application saying the landlord breached s. 20, for problems in the year before the application (RTA s. 29). The Board can then (s. 30):
- order an abatement of rent, including a monthly abatement until the repair is done;
- order specific repairs by a deadline, or authorize the tenant's own repair and make the landlord pay for it;
- order the landlord to pay for the tenant's damaged belongings and other reasonable out-of-pocket costs;
- stop rent increases until expired work orders and ordered repairs are completed;
- or end the tenancy.
Speed is what decides most of these cases. The Board's interpretation guideline says "It is reasonable management practice to answer maintenance requests in the order of their urgency (e.g., water leaks come before a loose wall tile), but all legitimate requests must be answered within a reasonable time", and that "if the landlord responded within a reasonable time, and the response was appropriate to effect the repair, no abatement or other remedy should be ordered."
A landlord with "a reasonable program of maintenance, including preventative maintenance" is in a strong position; one who "has done little maintenance for an extended period" should expect to pay for the tenants' loss of use. The Board must also consider whether the tenant told the landlord before applying (s. 30(2)), which is one more reason to log every report.
Tenants who stop paying rent over a leak take a bigger risk since September 21, 2026. To raise repair problems at a hearing about unpaid rent, a tenant must now give the landlord written notice in advance and pay half of the arrears claimed, no later than seven days before the hearing (RTA s. 82; O. Reg. 516/06, s. 8.3).
How do you deal with mould after a roof leak?
By drying fast, because a wet ceiling becomes a mould problem within days. Health Canada says "Mould will begin to grow in an area with excessive moisture within 48 hours". The Canadian Construction Association's mould guideline (CCA 82) asks that wet materials be dried "within 24 hours (48 hours maximum)" from when the water can be stopped, and says "absorbent ceiling tiles or fiberglass insulation cannot be effectively dried and should be immediately discarded and replaced." Ontario's maintenance standards require ceilings to be kept free of "mould, mildew and other fungi" (O. Reg. 517/06, s. 39).
| Mould area | Health Canada | Toronto Public Health |
|---|---|---|
| Small | One square metre or less | 1 m² or less: "can be cleaned using a household cleaner" |
| Medium | More than three patches, each under 1 m², totalling under 3 m² | 3 m² or less: occupant or maintenance staff |
| Large | A single patch over 3 m²: hire a professional | 4 m² or larger: "a professional trained in mould remediation" |
Size is not the only trigger. Health Canada also calls for a professional when mould comes back after cleaning, when it is suspected "inside walls or above ceilings", and when water has got into ceiling cavities that cannot be dried the usual way, which is exactly what a roof leak does. And none of it works until the roof is fixed: the guide says "the building envelope (i.e., roof, walls, windows, doors, foundation) must be repaired".
How is apartment building flat roof repair done with tenants at home?
Mostly from the roof, without going into units except to check the ceiling. The points that change when people live below:
- Winter repairs are often temporary. The CRCA treats 4.4°C as "the threshold for cold weather roofing applications", snow must be cleared before any membrane work, and each maker sets its own minimum temperatures. A temporary seal in January, followed by a proper repair when the weather allows, is normal; write both into the service log.
- Never open what cannot be closed the same day. CRCA: "No roofing materials should be removed unless it is possible to maintain the premises beneath the roof in a watertight condition."
- Plan access through the building. Crews use the stairwell and roof hatch, so protect common areas, keep the roof locked when they leave, and tell tenants in writing before anyone needs to enter a unit.
- Know where the cell antennas are. A CRCA bulletin says owners and property managers should know "whom to contact for information about antennas, their locations, and the RF radiation levels". Roofers ask the carrier to have them "temporarily powered down or moved", or stay 1.5 m from a single antenna and 3 m from a group.
- Keep torches away from occupied space where you can. Ontario's Fire Code sets a firewatch after torch work; our industrial roofing guide explains it, and cold-applied or heat-welded repairs avoid it.
A full re-roof with tenants at home is a bigger job with its own steps, covered in our apartment roof replacement guide.
When should an apartment roof be replaced instead of repaired?
When the repairs keep moving around the roof, or a moisture survey finds wet insulation, the roof is near the end of its life. CMHC's service-life figures for multi-unit residential buildings give a sense of the range:
| Roof or part | Typical life (years) | Median (years) |
|---|---|---|
| Modified bitumen, conventional | 17 to 27 | 22 |
| Built-up roof (BUR), conventional | 16 to 24 | 20 |
| Single-ply, conventional | 14 to 23 | 19 |
| Modified bitumen, inverted | 18 to 26 | 22 |
| Sheet metal flashing | 15 to 24 | 20 |
Ontario's rent rules use their own lives. For an above-guideline rent increase, O. Reg. 516/06 lists "Roof repairs" at 5 years (deemed 10, since nothing counts as less), a built-up roof at 15, a single-ply roof at 20 and an inverted four-ply roof at 20. A repair can be an eligible capital expenditure if it is "extraordinary or significant" and its benefit lasts at least five years, but "routine or ordinary work" is not, and the capital part of an increase is capped at 3% a year (RTA s. 126(11)).
Toronto offers another route. Its Hi-RIS program lends owners of apartment buildings at least 20 years old up to 10% of the property's assessed value or $2.5 million, whichever is less, at zero interest during construction, for energy and resilience work that includes "insulated roofing". The catch: owners "must agree not to apply for any rent increases above the guideline" for the work it funds.
CMHC's operations manual for rental buildings calls for a roofer's inspection every year and a thermal scan of the roof every 3 to 4 years. When the answer is replacement, our apartment roof replacement guide covers the work, our repair or replace guide covers the decision, and our budget guide covers the costs owners miss.
Has OYH Roofing worked on residential buildings?
Yes, though we have not published an apartment roof repair project, so this guide relies on the laws, by-laws and sources below. The photo at the top of this page shows the 17,500 sq ft PVC roof we installed on a new residential building in Sault Ste. Marie, which carries 30 years on labour and materials. Count the vent pipes: each one is flashed separately, and each is a place a future leak can start.
OYH Roofing is an Oakville-based industrial, commercial and institutional flat roofing contractor working across the GTA. For apartment building flat roof repair, we can trace leaks from the units below, make temporary repairs in winter, repair membranes, flashings and drains, and help you put the roof into your capital plan. See all our completed projects.
Frequently asked questions
Is a landlord responsible for mould in Ontario?
Yes, when it comes from the building, such as a roof leak. Ontario's maintenance standards require ceilings to be kept free of mould and the roof to be watertight, and city property standards by-laws say much the same. The landlord must fix the leak, dry or remove wet materials quickly and repair the damage. Tenants should report leaks and damp spots promptly, in writing.
How long does a landlord have to fix a roof leak in Ontario?
The Residential Tenancies Act sets no fixed number of days; repairs must be made within a reasonable time, and the Landlord and Tenant Board's guideline says water leaks come before minor repairs. Toronto, Mississauga and Ottawa require landlords of apartment buildings to respond to urgent requests within 24 hours, and a city work order sets its own deadline.
Can a tenant deduct repair costs from rent in Ontario?
Not without the Board. A tenant who withholds rent can face an application for unpaid rent, and since September 21, 2026 must give notice and pay half the arrears before raising repair problems at that hearing. The Landlord and Tenant Board can authorize a tenant's own repair and order the landlord to pay for it.
Does the landlord's insurance cover tenants' belongings after a roof leak?
Usually not. CMHC notes that for rental buildings, the landlord's property insurance "doesn't cover any of the personal belongings of your tenants", which is why tenants carry their own contents insurance. If the landlord breached the duty to repair, the Landlord and Tenant Board can order the landlord to pay for damaged belongings.
Can a landlord raise the rent after replacing the roof?
Possibly, through an above-guideline increase. Work needed to protect the building's "physical integrity", which includes the roof, can be an eligible capital expenditure, spread over its useful life (15 years for a built-up roof, 20 for single-ply) and capped at 3% a year. Routine repairs do not qualify, and the increase does not apply to tenants who moved in after the work.
A tenant just reported water through a top-floor ceiling?
Send us the unit number, photos of the ceiling and of the roof above if you can reach it safely, and when the water appeared. We will tell you whether it looks like the roof, a drain or something else, and what a temporary and a lasting repair involve.
Call 1-833-775-7663Request an assessment
Karol Rajkowski
Vice President · OYH Roofing
Karol Rajkowski is Vice President of OYH Roofing, an Oakville-based ICI flat-roofing contractor whose projects include the 53,000 sq ft roof of an industrial building in Mississauga, the 50,000 sq ft TPO roof at Millomat Stampings and the 52,300 sq ft roof at 777 Niagara St in Welland. Learn more about the OYH team.
Sources
- Ontario law: Residential Tenancies Act, 2006, ss. 20, 29, 30, 82, 126 and 224 to 226 (consolidation from September 21, 2026); O. Reg. 517/06 (Maintenance Standards), ss. 3, 4, 6, 7, 9 and 39; O. Reg. 516/06 (General), ss. 8.3, 18 and 27 and Schedule, Table 6 (consolidation from September 21, 2026); Landlord and Tenant Board, Interpretation Guideline 5, Breach of Maintenance Obligations (December 15, 2018).
- City rules: City of Toronto, Municipal Code Chapter 354, Apartment Buildings (consolidated June 15, 2026), RentSafeTO Building Owner Handbook (June 1, 2026), Chapter 629, Property Standards, s. 629-20, and Hi-RIS program; City of Mississauga, Rental Apartment Buildings By-law 0089-2022 and Apartment Building Owner's Quick Reference Guide (January 2026); City of Ottawa, Rental Housing Property Management By-law 2020-255.
- Roofing practice: CRCA, Canadian Roofing Reference Manual, 13.1.1 Locate the Problem Area, 13.1.2 Potential Problem Areas, 3.3 Cold Weather Conditions and 3.2.3 Keeping Roof Watertight (2020); CRCA, Radiofrequency Radiation and Electromagnetic Fields (June 2023).
- Rental building management: CMHC, Capital Replacement Planning Manual (2003), Appendix F; CMHC, Operations Manual for Owners and Managers of Multi-Unit Residential Buildings (revised 2017); Ottawa Community Housing, Unit Modification Policy: Satellite Dishes (2024).
- Mould: Health Canada, Guide to addressing moisture and mould indoors; Toronto Public Health, What is mould?; Canadian Construction Association, CCA 82, Mould Guidelines for the Canadian Construction Industry (2004 edition), s. 6.5.
- OYH Roofing project record: residential building, Sault Ste. Marie (17,500 sq ft, PVC).
OYH Roofing, 2120 Speers Rd, Oakville, ON L6L 2X8 · 1-833-775-7663 · info@oyhroofing.ca