Short answer

In Ontario, a school roof replacement is run by the school board and paid for mostly from the province's School Condition Improvement funding, 70 per cent of which must go to major building components such as roofs. Most replacements are tendered in spring and built between the last day of school in late June and the end of August, after the board has checked the roof for asbestos and, in some older schools, RAAC panels.

Who pays for a school roof replacement in Ontario?

The school board, with money the province gives it for school renewal. For the 2026-27 school year, Ontario's Ministry of Education is providing $1.4 billion through two programs, School Condition Improvement (SCI) and the School Renewal Allocation (SRA), plus a separate $300 million to remove and replace reinforced autoclaved aerated concrete (RAAC). Roofs are named in the SCI rules: boards must direct 70 per cent of their SCI funds to "major building components (e.g., foundations, roofs, windows)" and to building systems such as plumbing, heating and ventilation.

School renewal funding for Ontario school boards, 2026-27. Source: Ministry of Education memorandum 2026: B02 (May 13, 2026) and 2026-27 Education Capital Policies and Programs Manual (May 2026).
Program2026-27 amountWhat it pays for
School Condition Improvement (SCI)$1,070 millionRenewing building components that "have exceeded or will exceed their useful life cycle". 70 per cent must go to major components such as roofs, windows and foundations, and to building systems; the other 30 per cent may also go to interiors and site work
School Renewal Allocation (SRA)About $380 millionMaintaining, renewing and improving schools; the Ministry's own example is "roof repairs". Mostly capital work, with a small share allowed for operating costs
RAAC removal and replacement$300 millionRemoving and replacing RAAC panels, found mostly in school roofs
Time limit (SCI and SRA)Two yearsEach year's allocation must be spent within two years; 2026-27 money expires on August 31, 2028

SCI money is shared among boards in proportion to their assessed five-year renewal needs. It cannot be used to add floor area, to pay debt or on administrative buildings, and boards must post their current and planned renewal projects on their websites. That page is the quickest way for a parent, a consultant or a roofer to see which school roofs are coming up.

The board decides which roofs to replace and when, and it hires the roofer through a public tender; our institutional roofing guide explains how public owners buy roofing work. Private schools are different: the Ministry gives them no funding or financial support, so a private school pays for its roof like any other building owner.

How does a school board decide which roof to replace first?

From condition data. Every Ontario school at least eight years old gets a full facility condition assessment once in each five-year cycle, carried out for the Ministry by VFA Canada with a team of two engineers. The assessments are non-invasive and list the work each building will need over the next ten years, and each school's "Live Facility Condition Index" changes as the board reports finished projects.

Roofs tend to rise to the top. The Toronto District School Board puts roofing in its "Urgent" category, next to boilers, fire alarms and sprinklers, for systems that "have surpassed their useful service life"; rooftop units sit one level lower, at "High". Its renewal needs backlog listed about 25,600 repairs worth $4.45 billion as of January 2025, and almost half its school buildings are more than 60 years old.

Across the province, the Financial Accountability Office estimated that 37.4 per cent of schools were below a state of good repair on March 31, 2024, with a repair backlog of $6.5 billion. A walk-through cannot see wet insulation, so a roof consultant normally adds core cuts or a moisture survey before the scope is fixed.

Expect about a year from decision to roof. The Hamilton-Wentworth District School Board's September 2026 capital update lists roofing projects "initiated Spring 2026" with "Construction anticipated in Summer 2027", and splits larger roofs into phases over separate summers.

When are school roofs replaced?

Mostly in the summer. Under Ontario's school year regulation, the school year starts on or after September 1 and ends on or before June 30, so the longest stretch without classes runs from the last day of school to the day after Labour Day. In Halton, where OYH Roofing is based, the 2026-27 year started on September 8, 2026 and ends on June 29, 2027 for secondary schools and June 30 for elementary schools.

A school roof replacement tender is built around that window: bids close in spring, work starts around the end of June, and the contract sets a substantial completion date in August.

Schedules in recent Ontario school roof tenders, as published in public notices and tender listings (see Sources). Start dates from listings are the dates listed, not confirmed site starts.
Board and schoolRoof workStartSubstantial completion
Upper Canada DSB, Morrisburg Public School (2025)2-ply modified bitumen on six roof sections; rooftop units replacedOn or about July 2, 2025By August 22, 2025
Upper Canada DSB, Pakenham Public School (2026)About 13,250 sq ft of 2-ply modified bitumen; new drains and vent stacks; solar panels removed and reinstalledAround June 29, 2026By August 26, 2026
Toronto DSB, Regent Heights Public School (2026)Roof replacement; work affecting the school after hours or on weekendsNot publishedBy August 31, 2026
Peel DSB, Brisdale Public School, Brampton (2026)Roof replacement; bids closed May 14Listed June 17, 2026Not published
Dufferin-Peel Catholic DSB, Sts. Martha and Mary (2025)Roof replacement through prequalified general contractorsAwarded July 16, 20255-month duration

A job awarded in mid-July, or listed to start before the last day of school, runs partly while the school is in use. The Toronto District School Board says that because of the volume of roofs and a "lack of qualified roofing contractors", its roof projects "cannot be limited to the summer and must be completed year-round", as much as possible outside school hours.

Full replacements are another matter. On its RAAC page, the same board says "the building must be empty when replacing roofs", because of the work overhead and asbestos abatement, so that work "is primarily conducted during the summer months". After-hours work must still fit the local noise by-law.

What has to be checked on an older school roof before work starts?

Asbestos first. Before a board calls tenders for a school roof replacement, Ontario's asbestos regulation, O. Reg. 278/05, requires it to have the materials likely to be disturbed examined for asbestos, to have a report prepared, and to give every prospective constructor a copy. Older roofs are a common place to find it: the Halton District School Board lists "roofing products, such as tar paper, shingles and felt" among the materials that may contain asbestos, and says 71 of its buildings have asbestos.

How the work is classed depends on how the roofing comes off, not only on what it contains:

How removing non-friable asbestos-containing roofing (felts, mastics, flashing cement) is classed under O. Reg. 278/05, s. 12. Source: e-Laws consolidation current to July 1, 2026.
How the material is removedType of operation
Taken off without being broken, cut, drilled, abraded, ground, sanded or vibratedType 1
Broken or cut with non-powered hand tools, with the material wetted to control dustType 1
Broken or cut with non-powered hand tools, not wettedType 2
Cut or ground with power tools attached to dust collectors with HEPA filtersType 2
Cut or ground with power tools without HEPA dust collection, such as an ordinary power roof cutterType 3: the Ministry of Labour is notified first, and workers need asbestos abatement training
More than one square metre of friable asbestos material removed or disturbedType 3

The type drives the method, the price and whether anyone can be in the building. Halton's rule is plain: work that may disturb asbestos-containing materials "is not permitted to occur while the space is occupied by students, staff or other building occupants". If material that is not in the report turns up during the tear-off, the regulation requires immediate notice, orally and in writing, to the Ministry of Labour inspector, the owner and the joint health and safety committee.

Three more checks belong at the same stage: the full designated substances list that every public tender must include (see before roofing starts on an older public building), whether an old built-up roof is asphalt or coal tar, and whether the job needs a building permit (see our roof replacement permit guide).

What is RAAC, and why does it matter on a school roof?

RAAC, reinforced autoclaved aerated concrete, is a lightweight precast concrete that was widely used in Ontario from about the mid-1950s to the mid-1970s, including as roof planks. An engineering white paper prepared for Infrastructure Ontario in 2024 says it is less robust than steel deck or ordinary concrete, sags permanently over time, and is damaged mainly by moisture, from rain getting in and from condensation inside the roof. Buildings put up before 1955 or after 1975 are unlikely to have it.

RAAC became public news in Ontario when the Ontario Science Centre closed in June 2024. The engineers' report on its main building found that most panel damage came from "water ingress through the roof assembly", that openings cut through panels for roof penetrations had also weakened them, and that a heavy snow or rain load could put distressed panels "at an increased risk of sudden collapse". It recommended replacing all RAAC panels with new steel deck at the next roof renewal.

The Ministry had already asked every school board, in November 2023, to "implement an investigation, assessment, and management strategy for RAAC within their buildings", and it later said about 8 per cent of Ontario schools have RAAC. The Toronto District School Board reports 27 of its 579 schools with full or partial RAAC roofs as of January 2026, plans to replace them by 2029 at an estimated $120 million to $150 million, and until then sends roofing contractors to clear snow from some of those roofs after heavy snowfalls, with a report to a professional engineer each time.

For the roofer, RAAC changes the job:

  • Ask before you quote. On a school built between the mid-1950s and mid-1970s, ask the board whether the deck is RAAC. The white paper describes the panels as light grey or off-white, 457 mm (18 in.) wide, with a bubbly inside and no stones.
  • Keep loads off. The paper lists snow build-up, stored construction materials and new rooftop equipment among the loads to watch, so stockpiles on a RAAC deck need the engineer's approval.
  • No new openings without the engineer, and have the engineer check the weight of the new roof assembly: the paper notes that thicker insulation also means less snow melt.

A RAAC replacement is a structural deck replacement with an engineer's design, not a re-roof. See also our flat roof snow load guide.

How do Ontario school boards hire a roofer?

A school roof replacement is bought through a public tender, often limited to prequalified bidders. School boards follow the province's broader public sector procurement rules, and on contracts of $500,000 or more the Construction Act requires performance and labour and material payment bonds; our institutional roofing guide covers tenders, bonds, contracts and payment. Recent school tenders add these:

  • Prequalification. The Upper Canada and Kawartha Pine Ridge district school boards invited only prequalified bidders on 2025 roof tenders, and the Ottawa-Carleton District School Board ran a roofing contractor prequalification in fall 2025. The Dufferin-Peel Catholic board tenders roof replacements only to its prequalified general contractors, so the roofer works as their subcontractor.
  • Maker qualification. Two 2025 Avon Maitland District School Board re-roofing tenders required roofers qualified under SOPREMA's P.A.Q.+S warranty program, with proof before tender prices were opened.
  • Bonds and one site visit. The same two tenders asked for bid bonds of $58,000 and $76,000 and 50 per cent performance and labour and material payment bonds, and each had a single site walkthrough date.

Then there are police record checks. Since December 2025, O. Reg. 521/01 under the Education Act has required one for every "service provider" who comes into direct contact with pupils on a regular basis, including a contractor's employees and subcontractors. For most trades it is a criminal record and judicial matters check, renewed every five years, with an offence declaration by September 1 in the years between.

Boards apply this in their own way. Halton's procedure, revised in June 2026, asks contractors for an annual attestation, exempts a one-time visitor with no unsupervised access to students, and bars a contractor who fails to provide it from all board properties; York Catholic makes the check mandatory in its bid documents. Make sure every crew member's check can be back before the start date.

How is a school roof replaced while students and staff are in the building?

With odour control, a revised fire safety plan and a clear line between the work and the school. The Toronto District School Board's roof page lists what the roofer and its facility staff must do while roofing goes on over an occupied school:

  • Turn off or adjust the air handling systems during roofing, "so that fumes are not drawn into the school".
  • Seal windows and openings close to the kettle, and place the asphalt kettle downwind of the school when possible.
  • Run the air handling when the kettle is off, normally after school hours, plus portable fans with HEPA and charcoal filters.
  • Use low-odour hot asphalt, and low-VOC cold adhesives with no kettle "when feasible".
  • Hold a pre-construction meeting with school staff and an information meeting with the community before work starts.

TDSB describes the effects of asphalt fumes as "usually mild and temporary", such as headaches, dizziness and nausea. Kettle-free systems remove the biggest source of odour; our modified bitumen installation guide compares torch-on, self-adhered, cold adhesive and hot asphalt methods.

The Fire Code adds its own rules. Before construction "including hot surface applications" starts in or on a school, the fire safety plan must be revised with temporary measures for the occupants and for the fire hazards of the work, and then put in place. Fire access routes may not be obstructed by vehicles, fences or "building materials", so no bin or crane on one, and exits must stay clear.

Schools hold at least three full evacuation drills a term, and in summer too when in session, so the crew should know the drill plan. For the torch-on firewatch, see is torch-on roofing safe over a working building? On site, keep the hoist, bins and tear-off chutes away from entrances, playgrounds and bus loops, fence them off, and schedule heavy lifts outside school hours; our roof replacement guide covers the other disruptions in an occupied building.

Which roof systems do Ontario school boards use?

Low-slope, asphalt-based systems, mostly. The Ottawa-Carleton District School Board told roofers in 2025 that "most of our roofs require low-sloped roofing (2ply conventional BUR, 4 ply conventional BUR, and single ply)". The Toronto District School Board's elementary school guideline calls for a 4-ply built-up roof, and every recent school tender on this page that names a system calls for 2-ply modified bitumen.

Roof systems in Ontario school board documents. Sources: board guidelines, prequalifications and tender notices listed under Sources.
Board and documentRoof systemOther requirements
Toronto DSB, Elementary School Design Guideline4-ply built-up roof20-year no-dollar-limit manufacturer warranty; inspections in years 2, 5 and 10
Ottawa-Carleton DSB, roofing prequalification (2025)2-ply or 4-ply built-up, and single-plyLow-slope roofing on most of its roofs
Upper Canada DSB, Thousand Islands Secondary School (2024)2-ply modified bitumen, about 50,225 sq ftDesign slope of 2 per cent; aged exhaust units and six rooftop air handling units replaced
Avon Maitland DSB, Milverton Public School (2025)2-ply "asphalt-free" modified bitumen, about 9,711 sq ftRaised mechanical units and parapets for added insulation; roofer qualified under SOPREMA P.A.Q.+S
Upper Canada DSB, Pakenham Public School (2026)2-ply modified bitumenAll roof drains and vent stacks replaced; rooftop equipment, including solar panels, removed and reinstalled
Drone view of the 53,000 sq ft industrial building in Mississauga where OYH Roofing removed the old roof and installed a 2-ply modified bitumen system, with parking lots and neighbouring buildings around it
The 53,000 sq ft industrial roof in Mississauga where OYH Roofing removed the old roof and installed a 2-ply modified bitumen system, with 20 years on labour and materials. Two-ply modified bitumen is the system most school tenders on this page call for.

Rooftop units often go with the roof, as at Morrisburg and Thousand Islands; see how a roof is replaced around rooftop equipment. A full replacement is also the usual time to add insulation, which can mean raising curbs and parapets, as Milverton's scope did. Our best flat roof system guide compares the standards of four Ontario public owners.

What happens to solar panels on a school roof?

They come off and go back on, and the roof under them has to last. The Toronto District School Board has about 38 megawatts of solar panels on 358 buildings under Ontario's Feed-In Tariff (FIT) program, 347 of them through an agreement with Potentia. When that program started, roofs were fixed first: in 2013, CBC reported crews starting repairs on 32 buildings as part of a plan to put panels on 311 school rooftops, with the revenue used "to fund much-needed repairs and replacement on school rooftops".

The board's early FIT systems sell power under 20-year contracts, so a roof under panels needs a service life at least that long. When a roof under an array does wear out, the panels become part of the roofing contract: the Upper Canada District School Board's 2026 Pakenham tender required "careful removal and reinstallation of existing rooftop equipment (solar panels, exhaust fans, etc.)". Who owns the panels and who pays to move them depends on the solar agreement, so settle that before the tender. For the roof itself, see the best roof system under solar panels.

Does OYH Roofing work on school and institutional roofs?

Yes. OYH Roofing is an Oakville-based industrial, commercial and institutional roofing contractor, and institutional roofing is one of the services on our services page. We have not published a school project yet. Our published work in the system most school boards specify, 2-ply modified bitumen, includes:

On a school roof replacement, we can price the roofing scope for a board or for its general contractor. See all our completed projects.

Frequently asked questions

How long does a school roof replacement take?

Most school roof replacements are built in one summer, between the last day of school in late June and the end of August. Recent Ontario tenders set substantial completion dates of August 22, 26 and 31 for work starting around the end of June. Condition assessment, design and tendering usually take most of the year before, and a large roof may be split into phases over two or more summers.

Can a school roof be replaced while school is in session?

Sometimes. The Toronto District School Board says its roof work cannot be limited to the summer and continues through the school year in daylight hours, with air handling turned off, nearby windows sealed, low-odour materials and as much work as possible outside school hours. Work that may disturb asbestos is usually not allowed while students and staff are in the space, so full tear-offs of older roofs mostly happen in summer.

Who pays for school roof repairs in Ontario?

The school board, mostly from provincial renewal funding. For 2026-27, Ontario is providing $1.4 billion through School Condition Improvement and the School Renewal Allocation, plus $300 million to replace RAAC panels. Boards must spend 70 per cent of their School Condition Improvement money on major building components, such as roofs, windows and foundations, and on building systems. Private schools receive no provincial funding and pay for their own roofs.

How long do school roofs last?

Most school flat roofs last about 20 to 30 years, the usual range for a commercial flat roof in Ontario, depending on the system, the installation and the maintenance. Many schools keep roofs longer than they should: the Toronto District School Board says almost half its buildings are more than 60 years old, and it ranks roofs past their service life as urgent repairs. Provincial condition assessments flag roofs due for renewal.

What type of roof do schools have?

Most Ontario schools have low-slope, or flat, roofs covered with built-up roofing, 2-ply modified bitumen or a single-ply membrane such as TPO, PVC or EPDM. Each board sets the system in its own standard: the Toronto District School Board's elementary guideline calls for a 4-ply built-up roof, and recent tenders from other boards call for 2-ply modified bitumen. Some schools built from the mid-1950s to the mid-1970s have RAAC concrete roof decks.

Planning a school roof replacement?

Send us the school address, the roof area and any condition assessment, consultant report or tender documents you already have, and we will review the roof and the scope with your facility team or general contractor.

Call 1-833-775-7663Request an assessment
Karol Rajkowski, Vice President of OYH Roofing

Karol Rajkowski

Vice President · OYH Roofing

Karol Rajkowski is Vice President of OYH Roofing, an Oakville-based ICI flat-roofing contractor whose projects include the IKO 2-ply modified bitumen roof on the City of Mississauga building at 3185 Mavis Rd and the 52,300 sq ft IKO 2-ply modified bitumen roof at 777 Niagara St in Welland. Learn more about the OYH team.