Short answer

Solar panels on a commercial flat roof work well when the roof under them will last as long as the panels, about 25 years. Test the roof first, have an engineer check the weight, drifting snow and wind, and get the roof maker's approval before anything is set down or fastened. If the roof will not outlast the array, replace it first: taking an array off later has cost public owners up to $250,000.

Should you replace the roof before installing solar panels?

If the roof will not last as long as the panels, yes. The Canadian Roofing Contractors Association (CRCA) manual says the roof under an array "should have an expected service life equal to, or longer than the expected service life of the PV system, which is typically 25 years", and "It is not recommended to install a PV system on a roof system that has less than a 10-year service life." The reason is simple: "When it comes time to replace the roofing system, the entire PV system will have to be removed."

Others draw the line by the roof's age. The City of Toronto's solar guidance says "It is not recommended to install solar on a roof that is more than 10 years old (dependent on condition)", and insurer FM Global says a roof more than 10 years old "should be replaced or re-covered before installing PV systems that may last 25 to 30 years".

Ten years is the floor, not the target. A roof with 10 or 15 years left will still need replacing while the panels are mid-life, so the array comes off and goes back on once, at the owner's cost. Ontario's FIT contracts ran for 20 years, and Toronto's city-owned panels carry 25-year warranties.

Roof first or solar first: a guide by roof condition. Sources: CRCA Canadian Roofing Reference Manual, 11.2 (2020); FM Global Data Sheet 1-15 (April 2026); U.S. Department of Energy, Solar Ready Buildings Planning Guide (2009).
Roof todayWhat to doWhy
New roof, or a few years old, dry, with a current manufacturer warrantyGo ahead, with the roof maker's approval firstThe roof will outlast or nearly match the array; the maker still has to approve the plan (see warranties)
Middle-aged roof, about 10 to 20 years of life leftPrice both options: replace now, or plan one removal and reinstall of the array laterOne mid-life removal is certain; compare its cost with the value of the roof's remaining years
Less than 10 years left, wet insulation, or repeated leaksReplace the roof firstBelow the CRCA's floor; panels would hide the problems and block the repairs
Gravel-surfaced or ballasted roofAsk the designer before planning racking on itA U.S. federal guide warns that removing the stones to set panels "can be tedious and costly"

The roof's real remaining life comes from testing, not from its age alone. The CRCA asks for "A moisture survey and cut tests" on any existing roof before an array goes on; our leak detection guide explains the methods, and our repair or replace guide explains how the results decide the job. Which system to install under the panels is covered in our best flat roof system guide.

Can the roof structure carry the weight, snow and wind of a solar array?

Only an engineer can say. The CRCA says "The building structure must be reviewed by a professional engineer", because an array adds its own weight, "greater snow loads, increased wind loads and possible impacts on wind uplift". An array of 5 m² or more also counts as a "building" under Ontario's Building Code, so it needs a permit; our roof permit guide covers that.

Ontario's Building Code has clauses written for rooftop solar, and each one changes how the roof is designed:

Ontario Building Code clauses on rooftop solar panels. Source: 2024 Building Code Compendium (January 16, 2025 edition), Division B, Part 4, with Notes A-4.1.6.16. and A-4.1.7.13.
ClauseWhat it saysWhat it means for the roof
Snow on roofs with solar panels (4.1.6.16.)For tilted panels on a flat roof, the snow factor is "taken as 2.0 for roof areas within a distance of wph beyond the lowest edge of the panels", and snow trapped between rows is added to the loadSnow drifts in front of each row; the strip there is designed for twice the factor used on open roof areas
Snow removal (4.1.6.14.)Snow removal "shall not be used as a rationale to reduce design snow loads"Promising to shovel does not make a weak roof strong enough for an array
Wind on roof-mounted solar panels (4.1.7.13.)Roof wind loads must "account for the wind loads on the solar panels", with higher factors at the exposed edges of an arrayRows near the roof edge usually need more ballast or more attachments
Note A-4.1.7.13."the roof needs to be designed for the case where the solar array has been removed"; attached arrays put "concentrated loads at the points of attachment"; snow can block the gap under panels and raise wind loadsThe roof must hold down on its own when the array comes off for a re-roof
Seismic, ballasted arrays (4.1.8.18.(17))Friction may resist earthquake forces only if, among other limits, the roof slope is 3° or less, a parapet stands at least 400 mm high and the array is at least 450 mm from itA ballasted array on a roof without a parapet may need to be tied down

Weight is the other half. A U.S. National Renewable Energy Laboratory guide puts ballasted racking at about 4 to 6 lb per sq ft of collector area, and the Code's higher wind factors at the edges of an array add ballast there. Our rooftop equipment guide explains how much load a flat roof can take, and our snow load guide covers drifts.

Is ballasted or attached solar racking better for a flat roof?

Each one costs the roof something. The CRCA manual names three ways to hold an array down, and the choice decides how many holes the roof gets, how much weight it carries and whether it can be repaired without moving panels:

Solar racking on a flat roof and what each type means for the membrane. Sources: CRCA Canadian Roofing Reference Manual, 11.1 (2020); IIBEC Interface, "Forward-Thinking, Solar-Ready Commercial Roof Design" (December 2025, U.S. engineers); IIBEC Technical Advisory TA-27-2025; FM Global Data Sheet 1-15 (April 2026).
RackingHow it stays putWhat it means for the roof
Ballasted"The weights of the array, racking system and additional ballast material are used to prevent wind uplift and displacement""fewer roof penetrations have to be made watertight", but more dead load; trays "can shift in service ... potentially abrading or damaging the membrane"; the array has to move before the roof under it can be repaired. FM Global allows new ballasted arrays "only over adhered roof membranes" and none on gravel roofs
Attached (direct connection)Posts fastened to the roof structure through the membraneEach post is a flashing: the penetrations "require proper tie-in and flashing into the roofing system". Raised posts and frames allow "roof maintenance, repair, or replacement without disrupting the PV assembly"; often the preferred method, with "greater initial costs"
HybridA few structural connections plus ballast"the fewer the number of connections, the more ballast required and vice-versa"

Height matters as much as type. Low mounts sit in the drainage path and, the same engineers found, leak more unless each one is raised on a curb, while pitch pockets fail "far faster than the surrounding roofing membrane". Under ballast, FM Global wants roof membrane scraps or the maker's slip sheets beneath each pedestal ("Do not use rubber or plastic pads"), and the cover board should be fully adhered so shifting ballast cannot rub the membrane against its fastener plates.

What roof details do solar panels on a commercial flat roof need?

Room to work, clear drainage and protection wherever the array touches the membrane. A CRCA technical bulletin puts it plainly: "PV rack mounted systems should be designed to facilitate roof maintenance, repair, and even reroofing." Before anything goes on, "Areas of ponding water, or roof edge and flashing details have to be rectified".

  • Clear drainage. "The PV system must not interfere with the roof's drainage." Rows, conduit and cable trays have to stay off drains, crickets and scuppers.
  • Clearances. The CRCA asks for "sufficient clearance of the PV components from the roof, walls, roof penetrations and other PV components", so a roofer can reach seams, flashings and curbs.
  • Walkways. "There should always be walkways installed as part of the PV", and the roof must "withstand an increased level of construction and maintenance traffic".
  • A protection layer. The University of Toronto's roofing standard calls for "a sacrificial roofing membrane (loose-laid)" under solar equipment, and U.S. roofing consultants writing for IIBEC advise "a second layer of compatible roof membrane as a protection layer beneath the ballasted solar racking system".
  • Cables on supports, not on the membrane. U of T runs cables in "a cable tray system" on pavers. The CRCA advises against conduit "within roofing assemblies or directly below the roof deck", where the next re-roof's fasteners could hit it.

Sika, Carlisle and the CRCA also ask for a tougher roof under an array: a thicker membrane and a hard cover board. Our best flat roof system guide lists their requirements, and our rooftop equipment guide covers supports for pipes and cables.

Does a solar array void a commercial roof warranty?

Not by itself, but an array put on without the roof maker's approval can. Membrane makers treat an array like any other addition to a warranted roof: they want to see the plan first, often inspect afterwards, and say who may cut into the membrane.

What roof makers ask before solar goes on a warranted roof. Sources: Sika Canada, Warranty Selection Guide (03.2023); Carlisle, Solar Installations on Warranted Roofs (U.S., April 2025); IKO Commercial, InnoviTPO Building Owner's Guide (2024).
MakerWhat it asks
Sika CanadaPV is allowed only on Sarnafil adhered or mechanically attached systems, and "Sika approved cover board is required for any systems with a PV installation"
Carlisle (U.S. policy)On an existing roof, a letter of compliance returned before installation and an inspection after it ($0.05 per sq ft, $500 minimum); penetrations "installed or flashed by a Carlisle authorized applicator"; "Attachment methods that rely on a weld or adhesion directly to the roof membrane will not be accepted"
IKO (InnoviTPO)Contact IKO Commercial Technical Services before "additions to your rooftop"; for a leak, "Remove any overburden materials (pavers, green roof, solar array, etc.)", and that removal "is not covered" by its Diamond Shield warranty unless bought with it

Two warranties end up on one roof: the roof maker and roofer cover the membrane, and the solar installer covers its own work. The University of Toronto's standard puts the burden where it belongs: the "Solar panel contractor is responsible for protecting the newly installed roof system and to ensure the warranty remains intact." Write the same into the solar contract, and have the roofer who holds the warranty flash any penetrations. Our roof warranty guide explains what manufacturer warranties cover.

What happens when the roof under solar panels needs repair or replacement?

Part or all of the array comes off, and that work belongs to a solar or electrical contractor, not the roofer. The CRCA's solar bulletin warns that at re-roofing "the entire PV system may have to be removed to facilitate the reroofing process, and then be reinstalled." An IIBEC advisory adds that removing panels "requires the services of a specially trained and certified electrical contractor", and that even when switched off or disconnected, a PV system "is still 'live' with electricity".

The cost is real, and public owners have published it:

What removing rooftop solar for roof work has cost public owners. Sources: City of Brockville Staff Report 2024-155; Athabasca Town and Country Today (May 4, 2025); Community Media Portal, Schreiber (October 3, 2025).
BuildingWhat happenedCost
Brockville Memorial Centre (arena), OntarioPanels from 2010 decommissioned and removed for a roof replacementAbout $250,000, inside a $1.66 million roof estimate
Edwin Parr Composite School, Athabasca, Alberta780 panels over a roof needing repair; trustees chose removal and disposal$250,000 to remove and reinstall, or $45,000 to remove only
Schreiber Municipal Centre, OntarioPanels from 2012, running at 30% efficiency, removed for roof repairs$4,000, removal only

Two of those owners decided the panels were not worth putting back, the choice every owner faces when an older array meets a worn-out roof. When the panels stay, the work is phased: one section comes off, the roof there is replaced, and the panels go back before the next section starts. Panels stored on the roof add load, so ask the engineer where they can sit. Our arena roof guide has the full Brockville story.

Read the solar contract long before the roof wears out, especially when a solar company owns the panels or leases the roof. It should say who removes and reinstalls the array and who pays, how much notice the building owner must give, whether lost generation has to be paid for, and who is liable if the roof is damaged during the work. Even the IESO's notes for lawyers on small microFIT systems leave "who pays the cost for its temporary removal?" as a question to settle in the agreement.

Why do roofs leak under solar panels?

Because an array adds holes, weight and traffic, and then hides the roof. In Brockville, an inspection found that the panel brackets "were simply fastened through" a metal roof, leaks followed "for close to a decade", and "repairs cannot be performed without removing a large number of solar panels". U.S. building engineers writing in IIBEC Interface (December 2025) describe ballasted arrays that caused "ponding at areas of localized deflection" and pulled base flashing loose at the roof edge, "resulting in water leakage to the interior".

  • Moving ballast. Trays and blocks shift with wind and heat, and rub through the membrane or push it against fastener plates.
  • Blocked drains. Rows, conduit and cable trays laid across the roof can stop water reaching drains; FM Global warns that arrays "can block the path to roof drains and allow excessive ponding".
  • Attachment flashings. Every post is a flashing; FM Global says to "Inspect the sealing of roof penetrations for watertightness annually".
  • Snow. The CRCA notes that snow drifts "collect along the backside of the modules", and snow sliding off the panels adds "point loading on the front side of the array". Clearing it means shovels working close to the membrane and the panels.
  • Debris and nests. Leaves and bird nests collect under panels, where they hold water and, FM Global warns, can be set alight by the panels above.

Finding a leak is harder too: much of the membrane is out of sight, and cut tests or repairs under the array mean lifting panels. The CRCA says "a roofing contractor should always be present when the PV is serviced or repaired". Our leak detection guide covers the methods.

What electrical and fire rules apply on a roof with solar panels?

The first rule is that the array cannot be switched off. Ontario's Ministry of Labour warns that modules produce direct current "at any time they are exposed to light", and that disconnecting the main breaker "does not stop a PV system from producing electrical power". That shapes every job on the roof:

Ontario rules and guidance for work on a roof with solar panels. Sources: Ministry of Labour, Alert: Photovoltaic systems (updated September 15, 2026); O. Reg. 213/91, s. 182; O. Reg. 570/05, s. 1; ESA Bulletins 64-5-5 (October 2026), 64-4-5 and 64-6-5 (May 2025); IHSA, Safe Practices for Working On or Around Photovoltaic Systems (M072, 2018).
TopicWhat it saysWhat it means on the roof
Who may touch the arrayWorkers not authorized and trained "must not attempt to move, alter or maintain any PV system components" (Ministry of Labour); only certified electricians may "connect, maintain or modify electrical equipment" (O. Reg. 213/91, s. 182)Roofers work around the array, never on its wiring
Removing panels for roof workElectrical work includes "connecting or disconnecting" (O. Reg. 570/05); ESA: "Yes, a notification is required" to remove and reinstall a PV system "during repair of roof structure"A licensed electrical contractor disconnects, notifies ESA and reconnects
Cables on the roofCables "shall not lie loosely on the roofing material", with supports at most 1 m apart (ESA 64-4-5)Loose cables chafing the membrane break the electrical code as well as the roof
Rapid shutdownWiring more than 1 m from the array drops to 30 V or less within 30 s; wiring "within a PV array" may stay energized (ESA 64-6-5)Rapid shutdown does not make the panels safe to handle
Before going up"Workers must not enter roofing areas that have existing photovoltaic panels without a representative of the owner being present" (IHSA, a recommendation)Book the owner's or solar operator's person with the roofer
Rack heightRacks high enough "for re-roofing operations. A minimum of 46 cm (18 in) is recommended" (IHSA)Raised racks let the roof be repaired without moving panels

Fire is the other concern. No Ontario rule requires firefighter pathways or setbacks around rooftop panels: the Fire Code does not mention solar at all, and the fire service's own guidance note tells crews "do not cut into, remove, or walk on the solar PV system". IHSA still recommends a clear perimeter at the roof edge, hatches and skylights, and paths between arrays "for workers, firefighting services, and emergency rooftop egress".

The roof under the array matters if a fire starts. Insurer FM Global says panels "re-radiate heat back onto the roof surface, leading to accelerated lateral fire spread", and that polystyrene insulation and bitumen roof covers "can melt, burn and flow". An FM Approved Class 1A roof loses that rating once panels go above it, unless the two were approved together; FM's fixes include a noncombustible cover board directly under the membrane.

Such fires do happen in Ontario. On April 28, 2025, a fire "on the roof of the building in a few solar panels" at Windsor's WFCU Centre caused about $1 million in damage to panels and roofing; the cause was not made public. Torch-applied roofing near an array must also keep the flame off "gas lines and electrical cables" (Fire Code 5.11.2.2.); our industrial roofing guide covers the firewatch.

How does OYH Roofing help with solar on a flat roof?

We are roofers, not solar installers. We have not published a solar project, so this guide relies on the codes, maker policies and public reports listed below. With solar panels on a commercial flat roof, our part is the roof under the array: checking whether the existing roof will last as long as the panels, replacing it first when it will not, and flashing the attachment points the racking needs.

The photo at the top of this page shows one of four new buildings at Longo's Plaza in Welland, where we installed about 64,000 sq ft of GAF TPO with a 20-year warranty. A new, open roof like this is the best starting point for an array. OYH Roofing is an Oakville-based industrial, commercial and institutional flat roofing contractor working across the GTA. See all our completed projects.

Frequently asked questions

Can you put solar panels on a flat roof?

Yes. On a commercial flat roof the panels sit on racks that tilt them toward the sun and are held down by ballast, by posts fastened to the structure, or by both. Before they go on, an engineer has to confirm the structure can carry the array, the snow that drifts around it and the wind, and the roof under it should have about 25 years of life left.

Can you remove solar panels and reinstall them?

Yes, and it is common during a roof replacement. In Ontario a licensed electrical contractor disconnects and reconnects the array and notifies the Electrical Safety Authority, while the solar contractor removes and stores the panels and racking. Public owners have paid from $4,000 to remove a small old array to about $250,000 for a large one, so put it in the roof budget.

How long do commercial solar panels last?

Panels often carry 25-year warranties, and the CRCA plans the roof under them around a 25-year life; FM Global speaks of PV systems that "may last 25 to 30 years". Output drops with age: Schreiber's panels from 2012 were down to 30% efficiency by 2025 and were removed rather than put back.

Do solar panels void a roof warranty?

Not automatically. Roof makers such as Sika, Carlisle and IKO want to review the plan before panels go on, may inspect afterwards and set rules on who flashes penetrations, and skipping those steps can put the warranty at risk. Removing panels to reach a leak is usually the owner's cost: IKO's warranty does not cover removing overburden such as a solar array.

Who should disconnect solar panels before roof work?

A licensed electrical contractor. Disconnecting is electrical work under Ontario law, ESA requires a notification to remove and reinstall a PV system during roof repairs, and the Ministry of Labour says untrained workers must not move or alter any part of an array. Panels stay energized in daylight even when disconnected, so roofers work around them, not on them.

Planning solar on a roof that is already 10 or 15 years old?

Send us the roof's age, system and size, any past leak reports and the solar installer's layout. We will tell you whether the roof should be replaced first, and what the roof work under the array involves.

Call 1-833-775-7663Request an assessment
Karol Rajkowski, Vice President of OYH Roofing

Karol Rajkowski

Vice President · OYH Roofing

Karol Rajkowski is Vice President of OYH Roofing, an Oakville-based ICI flat-roofing contractor whose projects include the 53,000 sq ft roof of an industrial building in Mississauga, the 50,000 sq ft TPO roof at Millomat Stampings and the 52,300 sq ft roof at 777 Niagara St in Welland. Learn more about the OYH team.